Polusjärvi wind farm project

10
pcs
160
m
150
m
4,3
MW

Polusjärvi

Polusjärvi 9/2020

Polusjärvi

Suomen Hyötytuuli is building a wind farm of ten wind turbines in Pyhäjoki. Construction work began in January 2020. The installation and commissioning of wind turbines is scheduled to take place during summer 2021.

The project transferred from ABO Wind Oy to Suomen Hyötytuuli for development in September 2018. The municipality of Pyhäjoki is located in Northern Ostrobothnia. The planned wind farm is located in the Eastern part of the municipality of Pyhäjoki, on the northeast side of Liminkakylä, close to the village of Polusperä, approximately 20 kilometers away from the center of  Pyhäjoki.

Wind farm will consist of the turbines including their foundations, the connecting land cables, the wind farm’s substation and the maintenance roads connecting the wind power stations.

PERMIT PROCEDURE

The EIA procedure for the project has been completed in 2016. The EIA documents (only in Finnish) can be viewed via the following link:

Ympäristö.fi-sivusto

The land use plan and building permits of Polusjärvi wind farm project have legal force.

Energy Production

Jokela wind farm

12 pcs / 3,0 MW

Wind farm's current production 1.05 MW

Annankangas wind farm

10 pcs / 3,45 MW

Wind farm's current production 13.94 MW

Kuljunniemi wind farm

9 pcs / 2,3 MW

Wind farm's current production 4.67 MW

Nikkarinkaarto wind farm

10 pcs / 3,45 MW

Wind farm's current production 9.75 MW

Reposaari wind farm

10 pcs / 1-3,3 MW

Wind farm's current production 0.84 MW

Tahkoluoto offshore wind farm

11 pcs / 2,3-4,2 MW

Wind farm's current production 2.88 MW