All turbines of Tahkoluoto Offshore installed
All ten turbines of Tahkoluoto Offshore are now installed, and the sea cable has been laid. Erosion protection of the foundations and the sea cable are still to be finalized.
The foundation installation started in mid-May. Commissioning and testing takes place until September. The wind farm will be in production during September.